Topic · SchoolsActive
New school building
Milton is planning a new school with help from the Massachusetts School Building Authority (MSBA) to relieve crowding. The project is estimated at about $180 million, or about $130 million to Milton after state aid, and Gile Road is the main site option. DLR Group was picked as designer in October and is studying options, which now include pre-K and kindergarten. A town vote on paying for the school is expected in fall 2028.
Sources: School Building Committee video, Nov 2 (Milton Access TV) · School Committee video, Oct 28 (Milton Access TV) · School Committee member Nathan Hutto's Oct 7 recap · as of Nov 10
- State program
Dec 2024 - Designer picked
Oct 2026 - Options study
now - Site decision
summer 2027 - Town vote
fall 2028
Questions
Where would Milton's new school be built?
No site is final. Gile Road, a 6.4-acre town-owned site, is the main option, and the state also requires the study to look at repairing or adding on to Cunningham and Collicot. If voters approve the Labouré purchase on Dec 15, the Labouré campus will be studied too. Labouré property →
Town's Labouré purchase page · School Committee video, Oct 28 (Milton Access TV) · as of Oct 28
What kind of school is Milton planning?
That is still being studied. The options are a combined K-5 school with districtwide pre-K for 1,400 students, an added elementary school for 495, or a grades 7-8 school with districtwide pre-K for 660. Milton has also asked the state to add a pre-K and kindergarten option.
Town's Labouré purchase page · School Building Committee agenda, Nov 2 · as of Nov 2
How much would Milton's new school cost?
About $180 million in total, or about $130 million to Milton after state aid, by School Committee member Nathan Hutto's estimate. No cost has been given yet for adding pre-K and kindergarten.
School Committee member Nathan Hutto's Oct 7 recap · School Building Committee video, Nov 2 (Milton Access TV) · as of Nov 2
When do Milton voters decide on the new school?
A town vote on paying for Milton's new school is expected in fall 2028. The School Building Committee said Nov 2 that adding pre-K and kindergarten should not delay that vote.
School Building Committee video, Nov 2 (Milton Access TV) · as of Nov 2
Why does Milton say it needs a new school?
Milton's schools are crowded: enrollment is 4,374, about 650 more than when the current schools were built, the School Committee chair said Oct 19. The School Building Committee says Milton needs about 26 more classrooms.
Town Meeting video, Oct 19 (Milton Access TV) · School Building Committee video, Nov 2 (Milton Access TV) · as of Nov 2
Timeline
- Nov 10School panel stands by 26 more classrooms; a resident disputes it
- Nov 10Adding pre-K and kindergarten unlikely to delay 2028 school vote
- Nov 1State Panel Picks DLR Group to Design Milton School Project
- Oct 30Milton Seeks State Study of a PreK/K School, Labouré Included
- Oct 20Milton's State-Aided School Project Picks Its Architect as Labouré Emerges as an Alternative
- JunePMA is hired as the town's project manager.School Committee member Nathan Hutto's Oct 7 recap
- FebMilton signs a feasibility study agreement with the state.Town's Labouré purchase page
- Dec 2024Milton enters the state's school building program (MSBA).Town's Labouré purchase page