Milton's School Building Committee chair said Nov 2 the schools need 26 more classrooms, answering a resident who says the town undercounts the classrooms it has.
- The resident's case: At Town Meeting Oct 19, a resident said the elementary schools were built with 95 core classrooms, not the 87 the town told the state school building authority. With recent changes she counts 102, room for about 2,244 students, 23 more than are enrolled.
- The chair's count: The chair said the schools were designed for 84 classrooms in 2002, and about 11 more rooms were turned into classrooms by 2019, when 95 were in use. He said the resident added the needed rooms to 84 instead of 95.
- The need: A 2019 architect study said kindergarten through grade 5 needs about 115 classrooms, 20 more than in 2019. The other 6 of the 26 are for pre-K, art, music and special education.
- Outside review: The chair said the state school building authority's consultants also found Milton overcrowded.
- Next: The chair will send the resident a written reply. No date is set, and no vote was taken.
- Background: The school project is estimated at about $180M, about $130M to Milton after state aid. DLR Group has been picked as designer.