Architects showed Somerville's School Building Committee two possible looks for the new 925-student school at 115 Sycamore St on Nov 2. The committee did not pick one.
- The two looks: one uses darker brick in layers, a nod to the city's brickmaking past. The other is lighter, with patches of color drawn from nearby houses. Members were split, and the architects said the result may mix both.
- Upkeep: Superintendent Rubén Carmona asked for outside materials that are easy to maintain. He cited tile problems at the East Somerville Community School and Somerville High School.
- Cost comes in February: two cost estimates are due Feb 5. The design and budget must reach the state school building agency (MSBA) by Feb 24. That submission sets the most the state will pay.
- State review: the MSBA board approved the project's last design stage on Oct 28. The agency is not paying for about 10,000 square feet of planned space, and wants a bigger cafeteria than designed. The design team is contesting the cafeteria.
- Outside: the landscape designers showed five layouts for the turf field, basketball courts, playgrounds and a garden. No layout was chosen.
- Next: the committee meets again Dec 7.