 "id": "gile-road-school",
 "name": "New school building",
 "aka": [
  "Gile Road school project",
  "state-aided school project",
  "MSBA"
 ],
 "town": "Milton, MA",
 "url": "https://civichum.com/ma/milton/topics/gile-road-school/",
 "beats": [
  "Schools"
 ],
 "status": "active",
 "next": "Design stage",
 "updated": "2026-11-10",
 "description": "Milton's state-aided project to build a new school and relieve crowding, with Gile Road as the main site option.",
 "summary": {
  "text": "A state-aided new school to relieve crowding, with Gile Road as the main site option. About $180 million, roughly $130 million to Milton after state aid; the designer is studying options.",
  "as_of": "2026-11-10"
 },
 "lede": {
  "text": "Milton is planning a new school with help from the Massachusetts School Building Authority (MSBA) to relieve crowding. The project is estimated at about $180 million, or about $130 million to Milton after state aid, and Gile Road is the main site option. DLR Group was picked as designer in October and is studying options, which now include pre-K and kindergarten. A town vote on paying for the school is expected in fall 2028.",
  "as_of": "2026-11-10",
  "sources": [
   {
    "label": "School Building Committee video, Nov 2 (Milton Access TV)",
    "url": "https://www.youtube.com/watch?v=ydC_NZzRt_k"
   },
   {
    "label": "School Committee video, Oct 28 (Milton Access TV)",
    "url": "https://www.youtube.com/watch?v=tr6bKd6cXxQ"
   },
   {
    "label": "School Committee member Nathan Hutto's Oct 7 recap",
    "url": "https://nathanhutto.substack.com/p/milton-school-committee-unpacked-b2f"
   }
  ]
 },
 "track": {
  "steps": [
   {
    "id": "msba",
    "name": "State program",
    "when": "Dec 2024"
   },
   {
    "id": "designer",
    "name": "Designer picked",
    "when": "Oct 2026"
   },
   {
    "id": "options",
    "name": "Options study",
    "when": "now"
   },
   {
    "id": "site",
    "name": "Site decision",
    "when": "summer 2027"
   },
   {
    "id": "vote",
    "name": "Town vote",
    "when": "fall 2028"
   }
  ],
  "now": "options"
 },
 "facts": [
  {
   "id": "cost",
   "value": "About $180M",
   "label": "Project cost",
   "means": "Total estimate, per School Committee member Nathan Hutto",
   "as_of": "2026-10-20",
   "sources": [
    {
     "label": "School Committee member Nathan Hutto's Oct 7 recap",
     "url": "https://nathanhutto.substack.com/p/milton-school-committee-unpacked-b2f"
    }
   ]
  },
  {
   "id": "share",
   "value": "About $130M",
   "label": "Milton's share",
   "means": "After state aid, same estimate",
   "as_of": "2026-10-20",
   "sources": [
    {
     "label": "School Committee member Nathan Hutto's Oct 7 recap",
     "url": "https://nathanhutto.substack.com/p/milton-school-committee-unpacked-b2f"
    }
   ]
  },
  {
   "id": "state",
   "value": "45%",
   "label": "State reimbursement",
   "means": "Pledged by the state, the School Building Committee chair told Town Meeting",
   "as_of": "2026-10-19",
   "sources": [
    {
     "label": "Town Meeting video, Oct 19 (Milton Access TV)",
     "url": "https://www.youtube.com/watch?v=LWdqaQZVTq8"
    }
   ]
  },
  {
   "id": "enrollment",
   "value": "4,374",
   "label": "Students",
   "means": "About 650 more than when the current schools were built, per the School Committee chair",
   "as_of": "2026-10-19",
   "sources": [
    {
     "label": "Town Meeting video, Oct 19 (Milton Access TV)",
     "url": "https://www.youtube.com/watch?v=LWdqaQZVTq8"
    }
   ]
  },
  {
   "id": "rooms",
   "value": "26",
   "label": "Classrooms needed",
   "means": "About 20 regular classrooms plus rooms for pre-K, art, music and special education, per the School Building Committee",
   "as_of": "2026-11-02",
   "sources": [
    {
     "label": "School Building Committee video, Nov 2 (Milton Access TV)",
     "url": "https://www.youtube.com/watch?v=ydC_NZzRt_k"
    }
   ]
  },
  {
   "id": "gile",
   "value": "6.4 acres",
   "label": "Gile Road site",
   "means": "Town-owned land, the main site option",
   "as_of": "2026-10-14",
   "sources": [
    {
     "label": "School Building Committee agenda, Oct 14",
     "url": "https://www.miltonma.gov/AgendaCenter/ViewFile/Agenda/_10142026-6946"
    },
    {
     "label": "Town's Labouré purchase page",
     "url": "https://www.miltonma.gov/1386/Purchase-of-Laboure-College"
    }
   ]
  }
 ],
 "questions": [
  {
   "id": "where",
   "q": "Where would Milton's new school be built?",
   "a": "No site is final. Gile Road, a 6.4-acre town-owned site, is the main option, and the state also requires the study to look at repairing or adding on to Cunningham and Collicot. If voters approve the Labouré purchase on Dec 15, the Labouré campus will be studied too.",
   "as_of": "2026-10-28",
   "sources": [
    {
     "label": "Town's Labouré purchase page",
     "url": "https://www.miltonma.gov/1386/Purchase-of-Laboure-College"
    },
    {
     "label": "School Committee video, Oct 28 (Milton Access TV)",
     "url": "https://www.youtube.com/watch?v=tr6bKd6cXxQ"
    }
   ],
   "related": "laboure"
  },
  {
   "id": "kind",
   "q": "What kind of school is Milton planning?",
   "a": "That is still being studied. The options are a combined K-5 school with districtwide pre-K for 1,400 students, an added elementary school for 495, or a grades 7-8 school with districtwide pre-K for 660. Milton has also asked the state to add a pre-K and kindergarten option.",
   "as_of": "2026-11-02",
   "sources": [
    {
     "label": "Town's Labouré purchase page",
     "url": "https://www.miltonma.gov/1386/Purchase-of-Laboure-College"
    },
    {
     "label": "School Building Committee agenda, Nov 2",
     "url": "https://www.miltonma.gov/AgendaCenter/ViewFile/Agenda/_11022026-7019"
    }
   ]
  },
  {
   "id": "cost",
   "q": "How much would Milton's new school cost?",
   "a": "About $180 million in total, or about $130 million to Milton after state aid, by School Committee member Nathan Hutto's estimate. No cost has been given yet for adding pre-K and kindergarten.",
   "as_of": "2026-11-02",
   "sources": [
    {
     "label": "School Committee member Nathan Hutto's Oct 7 recap",
     "url": "https://nathanhutto.substack.com/p/milton-school-committee-unpacked-b2f"
    },
    {
     "label": "School Building Committee video, Nov 2 (Milton Access TV)",
     "url": "https://www.youtube.com/watch?v=ydC_NZzRt_k"
    }
   ]
  },
  {
   "id": "vote",
   "q": "When do Milton voters decide on the new school?",
   "a": "A town vote on paying for Milton's new school is expected in fall 2028. The School Building Committee said Nov 2 that adding pre-K and kindergarten should not delay that vote.",
   "as_of": "2026-11-02",
   "sources": [
    {
     "label": "School Building Committee video, Nov 2 (Milton Access TV)",
     "url": "https://www.youtube.com/watch?v=ydC_NZzRt_k"
    }
   ]
  },
  {
   "id": "why",
   "q": "Why does Milton say it needs a new school?",
   "a": "Milton's schools are crowded: enrollment is 4,374, about 650 more than when the current schools were built, the School Committee chair said Oct 19. The School Building Committee says Milton needs about 26 more classrooms.",
   "as_of": "2026-11-02",
   "sources": [
    {
     "label": "Town Meeting video, Oct 19 (Milton Access TV)",
     "url": "https://www.youtube.com/watch?v=LWdqaQZVTq8"
    },
    {
     "label": "School Building Committee video, Nov 2 (Milton Access TV)",
     "url": "https://www.youtube.com/watch?v=ydC_NZzRt_k"
    }
   ]
  }
 ],
 "timeline": [
  {
   "date": "2024-12",
   "text": "Milton enters the state's school building program (MSBA).",
   "sources": [
    {
     "label": "Town's Labouré purchase page",
     "url": "https://www.miltonma.gov/1386/Purchase-of-Laboure-College"
    }
   ]
  },
  {
   "date": "2026-02",
   "text": "Milton signs a feasibility study agreement with the state.",
   "sources": [
    {
     "label": "Town's Labouré purchase page",
     "url": "https://www.miltonma.gov/1386/Purchase-of-Laboure-College"
    }
   ]
  },
  {
   "date": "2026-06",
   "text": "PMA is hired as the town's project manager.",
   "sources": [
    {
     "label": "School Committee member Nathan Hutto's Oct 7 recap",
     "url": "https://nathanhutto.substack.com/p/milton-school-committee-unpacked-b2f"
    }
   ]
  }
 ],
 "sources": [
  {
   "label": "School Building Committee agenda, Nov 2",
   "url": "https://www.miltonma.gov/AgendaCenter/ViewFile/Agenda/_11022026-7019"
  },
  {
   "label": "School Committee presentation, Oct 7: MSBA and Labouré update",
   "url": "https://files-backend.assets.thrillshare.com/documents/asset/uploaded_file/4813/Mps/45c07e7b-26b7-4d9d-beed-f74bd52651bd/School-Building-Presentation-October-7-2026-MSBA-and-Laboure-Update.pdf"
  },
  {
   "label": "Town's Labouré purchase page",
   "url": "https://www.miltonma.gov/1386/Purchase-of-Laboure-College"
  }
 ],
 "stories": [
  {
   "headline": "School panel stands by 26 more classrooms; a resident disputes it",
   "url": "https://civichum.com/ma/milton/news/school-panel-stands-by-need-for-26-more-classrooms/",
   "published": "2026-11-10"
  },
  {
   "headline": "Adding pre-K and kindergarten unlikely to delay 2028 school vote",
   "url": "https://civichum.com/ma/milton/news/adding-pre-k-and-kindergarten-unlikely-to-delay-2028-school-vote/",
   "published": "2026-11-10"
  },
  {
   "headline": "State Panel Picks DLR Group to Design Milton School Project",
   "url": "https://civichum.com/ma/milton/news/state-panel-picks-dlr-group-to-design-milton-school-project/",
   "published": "2026-11-01"
  },
  {
   "headline": "Milton Seeks State Study of a PreK/K School, Labouré Included",
   "url": "https://civichum.com/ma/milton/news/milton-seeks-state-study-of-a-prek-k-school-laboure-included/",
   "published": "2026-10-30"
  },
  {
   "headline": "Milton's State-Aided School Project Picks Its Architect as Labouré Emerges as an Alternative",
   "url": "https://civichum.com/ma/milton/news/miltons-state-aided-school-project-picks-its-architect/",
   "published": "2026-10-20"
  }
 ],
 "related": [
  "laboure",
  "fy28-budget"
 ]
}